ESG Report of the
ENEA Capital Group for
2022

Development of energy production from renewable sources

  • INTERNAL INDICATOR 24

The increase in the installed RES capacity will be achieved through acquisitions, the development of own projects (mostly in rural areas) and in collaboration with business partners. We will also connect such installations owned by other entities to our distribution network.

Energy production from ENEA Group’s renewable sources

Item 2021 2022 Change %
ENEA Group
Total (net) electricity generation [GWh]] 26,393 26,214 -0.7%
Net generation from conventional sources [GWh] 23,978 24,265 1.2%
RES production [GWh] 2,415 1,949 -19.3%
ENEA Nowa Energia
RES production [GWh], including: 280 286 2.1%
Hydro power plants 114 108 -5.3%
Wind farms 157 167 6.4%
Biogas plants 9 9
PV farm1) 3 100%
ENEA Elektrownia Połaniec
Total (net) electricity generation [GWh]] 7,780 8,376 7.7%
RES production (biomass firing – Green Unit) [GWh] 1,582 1,128 -28.7%
RES production (biomass co-firing) [GWh] 326 309 -5.2%
ENEA Ciepło
Total (net) electricity generation [GWh]] 426 383 -10.1%
RES production – biomass firing [GWh] 227 224 -1.3%
1) On 22 March 2022, electricity generation was launched at the Jastrów photovoltaic farm with a capacity of 3 M.

Total production from renewable energy sources [GWh]

ENEA Nowa Energia investments

Name of investment Value [mln PLN]
Investment projects completed in 2022:
– PV Likowo – 1 MW capacity, independent project, construction outsourced; 3.1
– PV Jastrowie I – 3 MW capacity, independent project, construction by ENEA Serwis 2.8
– Power plant automation, modernization project, technological monitoring of a power plant 0.1
Investments planned for 2023:
– PV Dygowo I – 8 MW capacity, independent project, construction outsourced; 27.6
– PV Krzęcin – 6.605 MW capacity, independent project, construction outsourced 23.5
– PV-FW Lubno I – 3 MW capacity, independent project, construction outsourced 7.4
– PV Darżyno – 2 MW capacity, independent project, construction outsourced 7.1
– PV Lubno I and II – 2x1MW capacity, independent project, construction outsourced 5.7
– PV Dobrzyca – 0.2-0.3 MW capacity, independent project, construction outsourced 1.0
– Power plant automation, modernization project, technological monitoring of a power plant 0.2

ENEA S.A. is involved in several acquisition processes for photovoltaic farms and onshore wind farms. These processes are at different stages of progress. At the same time, ENEA Nowa Energia is implementing a number of projects (both its own and acquisitions) related to the construction/acquisition of onshore wind farms, the construction/acquisition of photovoltaic farms and the modernization of biogas plants owned by ENEA Group.

In 2022, the Group’s first photovoltaic power plants were put into operation: in Jastrowie (Wielkopolskie voivodship), Lików (Zachodniopomorskie voivodship) and Lubno (Lubuskie voivodship). Additional PV projects reached the stage of readiness for the launch of investment work in 2023.

At the beginning of 2022, the SPVs being a joint venture with PGE applied for a permit (location decision) for the construction and use of artificial islands. On 3 August 2022, ENEA S.A. acquired shares in these companies, i.e. Baltica-4 Wind Power Plant, Baltica-5 Wind Power Plant and Baltica-6 Wind Power Plant, from PGE, and became their co-owner. In February 2023, the Minister of Infrastructure announced the results of one of the award proceedings, stating that the Baltica-5 Wind Power Plant received the highest number of points, which increases the company’s prospects of receiving the permit.

We also produce renewable energy for our own needs.

Photovoltaic panels are used among others at Poznań and Maszewo sites of ENEA Pomiary.

In 2022, the design work was performed, the required permits and decisions were obtained and then a tender procedure was announced to build a photovoltaic farm at the premises of LW Bogdanka. The contractor was selected in December 2022. The time limit for the performance of the agreement was set for 30 July 2023.

In addition to developing our own RES capacity, we are involved in endeavors aimed at ensuring the country’s energy transition:

  • by connecting RES to ENEA Operator’s grid,
  • by providing substantive support to businesses with RES capacity – i.a. we launched the Generator Portal, a free proprietary IT tool that makes it easy to observe the reporting obligations for electricity generation and injection into the grid (in accordance with SOGL Guidelines).

Connected RES sources in the operating area of ENEA Operator in 2016-2022

The list does not include cogeneration sources or RES connected under the C1x and C2x tariffs.

The list does not include cogeneration sources or RES connected under the C1x and C2x tariffs.

The list does not include cogeneration sources or RES connected under the C1x and C2x tariffs.

The list does not include cogeneration sources or RES connected under the C1x and C2x tariffs.

For more information on the planned increase in installed renewable energy capacity and the phasing out of fossil fuels, please refer to the sections entitled Planned evolution of the ENEA Group’s energy generation structure and Roadmap to climate neutrality.

Search results