Activities for the reliability of energy supply

  • 3-3
  • INTERNAL INDICATOR 13

One of the strategic objectives of the ENEA Group is action for energy security of the country: to ensure continuity of electricity and heat supply and reliable operation of the distribution grid.

In order to ensure reliability of energy supply to Clients, ENEA Group companies:

  • introduce the latest technical standards,
  • operate strictly in accordance with procedures,
  • maintain the required state of the infrastructure,
  • perform preventive diagnostic measurements,
  • invest in the development of production assets,
  • connect new RES to the grid in order to ensure the required capacities of the power system,
  • modernize and automate power grids,
  • constantly improve qualifications of their teams,
  • appropriately plan shutdowns during modernization works,
  • analyze the causes of failures.

Selected measures for the continuity of energy production in 2022

ENEA Elektrownia Połaniec carried out a major overhaul of Unit 3 and the Green Unit (Unit 9), which included replacement or comprehensive repair of key parts of boilers and turbines.

ENEA Wytwarzanie modernized Units 6, 10 and 11, built the connection of the process steam collector of Units 1-10 with the steam collector of Unit 11 and the connection of the general electrical system of Units 1-10 with the same system of Unit 11.

At ENEA Ciepło bag filters were installed on WR-25 coal-fired boilers (K2 and K3) and 6.8 km of heating tunnel pipes was replaced with pre-insulated pipes. The company also conducted a periodic review of the Business Continuity Management System to assess its “maturity” and plan improvement initiatives. In addition, the company conducted tests and exercises within the infrastructure for heat generation, transmission and distribution – a notification test and a staff game test were conducted relating to the critical processes: Heat Generation and Management of Cyber Security Incidents. Procedures and instructions for heat generation, transmission and distribution were also reviewed and updated, with particular emphasis on emergency procedures.

MEC Piła carried out repairs and maintenance of heat sources, and replaced tunnel pipe networks with pre-insulated pipes to reduce losses in the heat distribution process. The water treatment plant was also modernized in order to ensure continuity of energy production.

PEC in Oborniki The company installed a photovoltaic system to ensure the continuity of the energy supply needed for heat production.

Łęczyńska Energetyka reviewed the technical condition of the tunnel district heating network and replaced the insulation on selected sections of the main line.

Measures to improve the reliability of distribution network operations

The regulations of activities to improve reliability of energy supply are in effect in ENEA Operator include the following:

  • The Business Continuity Plan, on which emergency procedures are based,
  • Procedure for planning and requesting work on HV, MV and LV grids for investing and operating purposes and for operational management of the grids in ENEA Operator sp. z o.o.,
  • Procedure for live-line working with power devices in ENEA Operator sp. z o.o.,
  • Procedure for live-line working on 15 and 20 KV overhead grids in ENEA Operator sp. z o.o.,
  • Procedure for recording work performed in the live-line working technology and calculating electricity supplied to users during live-line working in ENEA Operator sp. z o.o.,
  • Procedure of exchanging information and reporting events in the electric power grid by the ENEA Operator sp. z o.o.’s maintenance services and cooperation with crisis management teams in case of extensive failures,
  • Procedure for managing the removal of trees and bushes within the zones under ENEA Operator sp. z o.o.’s power lines,
  • Catalog of standard operating activities for HV, MV and LV grids in ENEA Operator sp. z o.o.,
  • Procedure for eliminating collisions,
  • Detailed regulations on correct operation of power installations,
  • Standards for the technical solutions for building power lines and devices applied in ENEA Operator’s distribution grid, including 110 kV overhead power lines and underground power cables, Medium voltage underground power cables, Low voltage underground power cables, Measurement and diagnostics equipment for high and medium voltage underground cables, Measurement and diagnostic equipment for medium voltage underground cables.

As part of the measures applied to improve the reliability of grid operation, especially of the MV grid, which has the greatest influence on the indicators of duration and frequency of interruptions in electricity supply, the following program and supporting activities are carried out, among others:

  • adjusting the needs of own substations to ensure 24-hour power backup,
  • adjustment of automation of AFO (automatic load-shedding),
  • implementation of the MV Grid Development Concept, which takes into account development of automated solutions within the grid,
  • cables of MV grids passing through forest areas,
  • removal of equipment constraints,
  • implementation of the FDIR (Fault Detection, Isolation & Restoration) function in selected MV line sections,
  • liquidation of the 6 kV grid in the Poznań urban area,
  • activities in respect to measurements and diagnostics of medium voltage cable lines,
  • systemic measures related to the removal of trees and bushes within the zones under power lines.

ENEA Operator makes all efforts to limit the consequences of failures and restore power supply to customers as quickly as possible. For this purpose, it supplies energy to a separate electric power grid using electricity generators, provided that it is technically feasible, and cooperates with other operators of distribution systems and the transmission system. In order to limit interruptions in power supply to users to the minimum, the company also regularly increases the scope of work performed in the live-line working technology (MV and LV) and carries out preventive diagnostic measurements. The work on locating damage in the grid, making the necessary switching and repairs to restore power supply to the consumers is undertaken immediately after the failure occurs, by ENEA Operator employees or by external contractors. For each failure, a cause analysis is conducted as an element of the assessment of the technical condition and forms the basis for devising the scope of an upgrade/replacement of devices under the modernization and capital expenditure programs implemented by the company or its operating decisions.

The safety of electricity supply to customers is also significantly improved by the standards for any technical solutions applied, materials used and works performed on the distribution grid the company has introduced. The use of standardized grid equipment enables a faster removal of failures. During the process aimed at developing the said standards, each solution is subjected to an in-depth analysis and technological tests. All standards are then subjected to periodic analyses at least every 24 months counting from their entry into force, which enables their detailed formulation and update in a manner that makes the requirements and guidelines contained therein reflect the changing needs of the power grid operation. Additionally, every year tests of the correctness and speed of response to a mass failure are conducted in selected business units of the company.

On 19 February 2022, a storm swept through northwestern Poland, cutting off power to almost 4,000 towns and cities and 600,000 recipients. Several hundred power engineers from more than 200 brigades immediately set to work to repair the outage. Thanks to their professionalism and dedication, ENEA Operator restored power to over 520,000 recipients within 24 hours.

Jacek Górski Vice‐President of the Management Board of ENEA Operator Sp. z o.o. for Network Infrastructure

Due to a large number of power failures caused by damage to buried cables during construction works, in particular in large cities, the company conducts a campaign to raise awareness of this issue among building contractors. As a result, construction companies have been reporting cable damage much more frequently and identify the exact location of the incident. This allows us to reach the place of damage and repair it faster.

In 2022, ENEA Operator continued its efforts aimed at improving the operational reliability of the distribution grid. To this end, it primarily carried out planned diagnostics of MV cable lines and ongoing modernization of power facilities and equipment in line with the existing modernization programs. It also maintained the regular strengthening of the support infrastructure for distribution activities, i.e. purchase of specialist equipment (including vehicles) and construction and modernization of support facilities.

Critical investments undertaken by ENEA Operator

In 2022, ENEA Operator carried out several strategic investments in the Lubuskie, Kujawsko-Pomorskie, Zachodniopomorskie, Wielkopolskie and Pomorskie voivodships. The most important ones include:

  • construction of a 110/15 kV substation at Suchy Las,
  • construction of a RS 110 kV switching substation in Garaszewo together with 110 kV line branches from SE 400/110 kV in Kromolice,
  • construction of a RS 110 kV switching substation in Bierzwnik,
  • reconstruction of 110 kV overhead lines: Recław – Nowogard, Gryfino – Żydowce and Dolna Odra – Gryfino,
  • reconstruction of the 110/15 kV substation in Międzyrzecz,
  • reconstruction of the 110/15 kV substation in Pakość,
  • reconstruction of the 110/15 kV substation in Kruszwica,
  • reconstruction of the 110/15 kV substation in Mogilno,
  • reconstruction of the 110/15 kV substation in Stargard Zachód,
  • reconstruction of the 110/15 kV substation in Recław,
  • reconstruction of the 110/15 kV substation in Gumieńce,
  • reconstruction of the 110/15 kV substation in Gryfice,
  • reconstruction of the 110/15 kV substation in Górczyn,
  • reconstruction of the 110/15 kV substation in Oborniki,
  • reconstruction of the 110/15 kV substation in Chodzież,
  • reconstruction of the 110/15 kV substation in Fałkowo,
  • construction of smart grids in Bydgoszcz, Krosno, Słubice and Żary counties and in the city of Zielona Góra.
  • INTERNAL INDICATOR 33
1.4
A total of over PLN bln
allocated by ENEA Operator for all planned investments that will directly or indirectly increase the reliability of power supply

Grid reliability indicators

The pace of improvement of the electricity supply reliability indicators is a result of a consistent implementation of extensive efforts in the areas of capital expenditures, operation and work organization.

  • SECTORAL INDICATOR EU28
  • SECTORAL INDICATOR EU29

Ratios1) Value achieved in 2022 Expected value of the ratio in the year:
SAIDI 89.07 min. 2030 74.59 min.
2040 70 min.
SAIFI 1.98 2030 2.02
2040 1.93
1)Reflects scheduled and unscheduled interruptions in electricity supply for high and medium voltages.